Cable routing Auerbruecke

Between the power station Auerbruecke and Nonnenmuehlsteg all supply lines had to be rearranged. The infrastructure project was necessary and completed simultaneously to the construction of the upstream fish migration necessary and realized. All work was carried out while maintaining the utility.

We were assigned with all engineering services ( turn-key engineering services). Special challenges were the traffic management which had to be coordinated at the same time with bridge rehabilitations of the city Pforzheim. Missing storage space made the sitting of the crane on the piers of the hydropower station Auerbruecke necessary.

Project type

  • Client: municipal utilities Pforzheim

  • Rehabilitation for the purpose of maintaining the security of supply

  • Location: Pforzheim city center

  • Implementation: 2015

Technical details

  • Water supply main DN600

  • 110 kV cable

  • Medium-high voltage cable interconnecting the ParkHotel

  • Telecommunication lines

  • Wired intranet of the city

Services performed

  • Design for approval & execution planning and computation

  • Site supervision

  • Execution design & construction site coordination

  • Cost Management